Question

An offset is measured with an accuracy of 1 in 40. If the scale of plotting is 1 cm = 20 m, find the limiting length of the offset so that the displacement of the point on the paper from both sources of error may not exceed 0.25 mm?

a.

14.10 m

b.

14.14 m

c.

14.40 m

d.

14.44 m

Posted under Surveying

Answer: (b).14.14 m

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. An offset is measured with an accuracy of 1 in 40. If the scale of plotting is 1 cm = 20 m, find the limiting length of the offset so that the displacement of the point on the...

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. What triangles are generally preferred to get good results in plotting?

Q. The line must run through level ground as possible is the condition to be fulfilled by survey lines or survey stations.

Q. The main lines should form well-conditioned triangles is the condition to be fulfilled by survey lines or survey stations.

Q. Survey lines must be as few as possible is the condition to be fulfilled by survey lines or survey stations.

Q. As far as possible main survey lines should pass through the obstacles to get know how many obstacles present.

Q. How many kinds of obstacles of chaining are there?

Q. Which of the following is not one among the three major kinds of obstacles of chaining?

Q. Both ends of the lines may be visible from intermediate points on the line. This case comes under which among the three kinds of obstacles to chaining?

Q. When it is possible to chain round the obstacle, i.e a pond, hedge etc. This case comes under which among the three kinds of obstacles to chaining?

Q. Both ends of the line may not be visible from intermediate points on the line. This case comes under which among the three kinds of obstacles to chaining?

Q. When it is not possible to chain round the obstacle e.g. a river. This case comes under which among the three kinds of obstacles to chaining?

Q. To continue a survey line AB past an obstacle, a line BC 100 m long was set out perpendicular to AB and from C angles BCD and BCE were set out at 60° and 45° respectively. Determine the lengths which must be chained off along CD in order that ED may be in AB produced?

Q. To continue a survey line AB past an obstacle, a line BC 100 m long was set out perpendicular to AB and from C angles BCD and BCE were set out at 60° and 45° respectively. Determine the lengths which must be chained off along CE in order that ED may be in AB produced?

Q. To continue a survey line AB past an obstacle, a line BC 300 m long was set out perpendicular to AB and from C angles BCD and BCE were set out at 60° and 45° respectively. Determine the obstructed length BE?

Q. If we select two points A and B on either side of the obstacle and equal perpendiculars AC and BD are set out. Then AB is equal to?

Q. The direction of a survey line can either be established with relation to _______

Q. What is the direction of line relative to a given meridian?

Q. Which line passes through true north and true south?

Q. Which meridian direction can be established with the help of a magnetic compass?

Q. Which meridians are used to determine the relative positions of the lines in a small area?

Recommended Subjects

Are you eager to expand your knowledge beyond Surveying? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!