a.
Bowditch’s method, Transit method
b.
Bowditch’s method, Graphical method
c.
Axis method, Transit method, Gale’s method, Co-ordinate method
d.
Bowditch’s method, Axis method, Graphical method, Transit method
Posted under Surveying
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. Which of the following implies the correct set of methods employed for balancing the traverse?
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. Angles are less affected by the corrections applied due to the Transit method than Bowditch’s method.
View solution
Q. Which of the following method doesn’t require the calculation of latitudes and departures?
View solution
Q. Balancing methods can be applied only when________
View solution
Q. Which method can also be known as Compass rule?
View solution
Q. Bowditch method can be applied even linear and angular measurements are not precise.
View solution
Q. In order to complete traverse computations, which of the following steps is to be carried out first?
View solution
Q. Sum of interior angles must be equal to____________
View solution
Q. Independent co-ordinates can be calculated by using___________
View solution
Q. Among the following, the most commonly used method of balancing a traverse is_________
View solution
Q. Calculate the correction for departure of BC, using Bowditch’s rule.
View solution
Q. Using transit method, calculate the correction for latitude of BC.
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Surveying? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!