Question

Calculate number of Kanbans if the hourly demand is 200 units, lead time is 12 hours, container capacity is 144 units, and variation in lead time is 15%.

a.

23

b.

22

c.

21

d.

20

Answer: (d).20

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Calculate number of Kanbans if the hourly demand is 200 units, lead time is 12 hours, container capacity is 144 units, and variation in lead time is 15%.

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. _______ signals the need to produce more parts and ______ signals the need to deliver more parts to the next work center.

Q. Which of the following does not belong to the five principles of lean?

Q. Which of the following is not an example of visual factory tools?

Q. Which of the following is not a benefit of a visual factory?

Q. One-piece flow is also known as single-piece flow in manufacturing.

Q. Which of the following is not an advantage of one-piece flow used in production?

Q. Which of the following refers to the term ‘autonomation’?

Q. Which of the following refers to ‘automation with a human touch’?

Q. The first step in applying Jidoka is _______

Q. Which of the following is not the aim of demand management?

Q. Which of the following is a type of plant layout in which machines and equipment are arranged according to their function?

Q. Which type of plant layout utilizes the merits of both process and product layout?

Q. In which type of plant layout machines are grouped into cells?

Q. Which of the following is not an advantage of cellular manufacturing?

Q. Product layout is generally used for standardized goods.

Q. Which type of plant layout is also known as static layout?

Q. Cellular manufacturing _______ teamwork and communication between employees and departments.

Q. ___ is a tool for monitoring how lean principles are working in an organization.

Q. Which of the following is not a goal of lean audit?

Q. Which lean philosophy says that things must be done right the first time and every time?

Recommended Subjects

Are you eager to expand your knowledge beyond Total Quality Management? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!