What principle does the Pay-back Method rely on to determine the worthiness of a project?

a.

The longer the pay-back period, the better the project

b.

The shorter the pay-back period, the better the project

c.

The pay-back period is irrelevant to project worthiness

d.

The pay-back period is determined by the average rate of return

Answer: (b).The shorter the pay-back period, the better the project Explanation:Under the Pay-back Method, the worthiness of the project depends on the principle that the shorter the pay-back period, the better or more desirable is the project.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. What principle does the Pay-back Method rely on to determine the worthiness of a project?

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. What are the steps involved in the capital budgeting process?

Q. How is capital budgeting defined?

Q. How is the terminal value (TV) of the Cash inflows expected from the project calculated in the Modified Internal Rate of Return (MIRR) method?

Q. What does the MIRR calculation involve?

Q. What is the purpose of the Modified Internal Rate of Return (MIRR) technique?

Q. What is a drawback of the Internal Rate of Return (IRR) when cash flows are non-conventional?

Q. What is a limitation of the Internal Rate of Return (IRR) when comparing two or more projects to select the best one?

Q. What is the purpose of comparing the Internal Rate of Return (IRR) to a hurdle rate?

Q. How is the Internal Rate of Return (IRR) calculated?

Q. What is the primary advantage of using the IRR as a criterion for project selection and performance evaluation?

Q. What does the Internal Rate of Return (IRR) on a project represent?

Q. What does the Capital Asset Pricing Model (CAPM) express regarding the expected return on any bundle of assets or cash flows?

Q. Why do firms or investors generally stick to the first approach (compute actual expected cash flow and discount at the appropriate risk-adjusted discount rate)?

Q. What are the two ways to compute the present value of expected inflow in any investment plan?

Q. How are the calculation of expected cash flow and discount rates considered in modern financial risk management?

Q. Which accounting data, with historical aspects, is of little use for forecasting cash inflows?

Q. What is one of the major aspects to keep in mind when preparing an expected cash flow estimate for a project?

Q. What must the evaluator examine in relation to cost of capital and NPV?

Q. What does Net Present Value (NPV) represent in terms of compensation for time and risks?

Q. What does a positive Net Present Value indicate according to NPV rules?

Recommended Subjects

Are you eager to expand your knowledge beyond IC 89 Management Accounting? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!