Pick up the correct statement from the following :

a.

the sewer pipes of sizes less than 0.4 m diameter are designed as running full at maximum discharge

b.

the sewer pipes of sizes greater than 0.4 m diameter are designed as running 2/3rd or 3/4th full at maximum discharge

c.

the minimum design velocity of sewer pipes is taken as 0.8 m/sec

d.

all the above.

Posted under Civil Engineering

Answer: (d).all the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Pick up the correct statement from the following :

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The sewer pipes

Q. The normal values of over flow rates for secondary sedimentation tanks, ranges between

Q. The Brake Horse power of the motor (efficiency 60%) required for a pump of capacity 0.075 cumec for a total lift of 12 m, is

Q. The normal value of over flow rates for plain primary sedimentation tanks, ranges between

Q. The asbestos cement sewers are

Q. Bottom openings 15 cm x 15 cm in the standing baffle wall are provided

Q. Faculative bacterias survive in

Q. The ratio of maximum sewage flow to average sewage flow for trunk mains having diameters more than 1.25 m, is

Q. For sewers, inverted siphon is provided for

Q. The coagulant which is generally not used for treating the sewage, is

Q. Fresh sewage is generally

Q. In a trickling filter

Q. If the flame of a miner's safety lamp in a manhole extinguishes within 5 minutes, the sewer certainly contains

Q. In Chezy's formula V = C √rs for calculating the velocity of flow in circular sewer of diameter D running full, the value of hydraulic mean radius is

Q. The sewer which collects the discharge from a collecting system and delivers it to a treatment plant, is known

Q. If the depletion of oxygen is found to be 5 ppm after incubating a 2.5% solution of sewage sample for 5 days at 21°C, B.O.D. of the sewage is

Q. Setting out the alignments of sewers may start from

Q. If the flame of a miner's safety lamp in the upper layers of the sewer forms an explosive, the sewer certainly contains

Q. In normal conditions, the period for sludge digestion, is

Q. The bottom of the sewage inlet chamber of septic tanks, is provided an outward slope

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!