Question

Refer to the cash flow diagram of uniform gradient in a cash flow (in the given figure), the gradient is :

a.

Rs 10000 per year

b.

Rs 15000 per year

c.

Rs 20000 per year

d.

Rs 25000 per year

Posted under Civil Engineering

Answer: (d).Rs 25000 per year

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Refer to the cash flow diagram of uniform gradient in a cash flow (in the given figure), the gradient is :

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. In the cash-flow diagram shown in the given figure

Q. Pick up the correct statement from the following:

Q. If interest is paid more than once in a year, i is the rate of interest per year, n is the number of periods in years and m is a number of periods per years, compound amount factor (CAF) is :

Q. The capital Recovery Factor (equal payments) of Capital Recovery Annuity is :

Q. Current ratio is :

Q. If S is the future capital accumulated in n years at the rate of interest i per annum, then present worth is :

Q. Pick up the correct statement from the following:

Q. In the cash flow diagram shown in the given figure

Q. If P is principal amount, i is the rate of interest per annum and n is the number of periods in years, the compound amount factor (CAF) is :

Q. Pick up the correct statement from the following:

Q. Present worth Annuity (PWA) is generally known as

Q. Pick up the ratio which gives us sufficient information by which to judge the financial condition and performance of the firm, from the following:

Q. Pick up the correct statement from the following:

Q. The financial analysis helps to judge:

Q. The interest calculated on the basis of 365 days a year, is known as :

Q. In a cash-flow diagram :

Q. Which one of the following questions is relevant to the construction estimates :

Q. The ratio obtained by dividing 'quick assests' by current liabilities is called

Q. Which one of the following definitions, is correct ?

Q. Pick up the element of the cost from the following:

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!