Question

A man completes 5/8 of a job in 10 days. At this rate, how many more days will it takes him to finish the job?

a.

5

b.

6

c.

7

d.

7(1/2)

Posted under Aptitude

Answer: (b).6

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. A man completes 5/8 of a job in 10 days. At this rate, how many more days will it takes him to finish the job?