Question

The bond in which headers and stretchers are laid in alternate courses and every stretcher course is started with a three fourth brick bat, is known as

a.

English cross bond

b.

Dutch bond

c.

Monk bond

d.

Rat-trap bond.

Posted under Civil Engineering

Answer: (b).Dutch bond