Question
1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking
The correct sequence is :
a.
1 2 3 4 5
b.
2 3 5 4 1
c.
4 2 1 3 5
d.
2 3 1 4 5
Posted under Civil Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. The following operations are required for tunnelling in rocky terrain : 1. Removing the foul gases 2. Marking the tunnel profile 3. Setting up and drilling 4. Checking...
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. The advantages of providing a pair of tunnels as compared to only one large highway tunnel is :
View solution
Q. Which one of the following statements is not correct in respect of setting of an inclined tunnel:
View solution
Q. Forepoling method is generally adopted for tunnelling in :
View solution
Q. Concrete lining is provided concurrently with the driving operation in case of
View solution
Q. The concentration of the dust particles of the size 0.5 to 5 microns adjacent to the working face should not be more than
View solution
Q. Which one of the following statements is not correct with regard to heading and hench-ing method of tunnelling.
View solution
Q. The most commonly adopted pattern of cut holes is :
View solution
Q. Which one of the following linings is suitable for shield driven tunnels particularly in the subaqueous regions :
View solution
Q. In case of railways,
View solution
Q. The following tunnels were constructed in different countries for different purposes :
1. Emperor Claudius built the first Roman tunnel
2. The first highway tunnel was constructed in Hungary
3. The first underground railway tunnel was constructed in Great Britain
4. The first navigational tunnel was constructed in France.
The correct chronological development of these tunnels is:
View solution
Q. The following operations are generally employed for tunnelling in hard rock.
1. Removing ground water.
2. Loading holes and firing the explosive
3. Setting up and drilling
4. Grouting and lining
5. Removing muck
6. Ventilation and removing explosion dust
The correct sequence is :
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!