For how many days curing of concrete lining takes place?

a.

30 days

b.

28 days

c.

27 days

d.

26 days

Posted under Irrigation Engineering

Answer: (b).28 days

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. For how many days curing of concrete lining takes place?

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. In the laying of concrete, what paper is laid to make filter blanket effective?

Q. In soil-cement lining the Portland cement is added to the soil up to the extent of ____________

Q. Which type of lining is restricted to the availability of suitable soils in the area?

Q. Which lining is restricted to small canals and water-courses?

Q. A flexible membrane impregnated with tar or bitumen is spread over the subgrade in _________________

Q. Puddle clay is laid on the subgrade to form a fairly water-tight coating.

Q. What is the safe limiting velocity for cement concrete lining?

Q. The most economical type of lining is the one which shows ____________

Q. Which of the following guideline is not recommended for the choice of lining when the bed width of the canal is up to 3 m?

Q. Which of the following is not a cause for the hydrostatic pressure on the lining?

Q. Drainage relief pockets are provided ___________

Q. The permeability of lining is also governed by the depth of water in the canal and type of subgrade soil.

Q. Pressure relief valves may help in ___________

Q. Pipe drains run _______________

Q. Which of the following statement is wrong about the requirement of good lining?

Q. Which type of lining is adopted when the channels have become stable and no danger of scouring is expected?

Q. Which of the following statement is incorrect about Expansive soils?

Q. The larger the thickness of CNS introduced over the expansive soil, the more will be the resulting swelling in soil.

Q. What is the recommended value of CNS thickness to be used for lining over expansive soil with swelling pressure of 200-300 KN/m²?

Q. Safety ladders are generally provided on ___________

Recommended Subjects

Are you eager to expand your knowledge beyond Irrigation Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!