Question

For dewatering more than 6m below the water table, which of the following method is used?

a.

Well point system

b.

Multi stage well point system

c.

Vacuum method

d.

Deep well system

Answer: (b).Multi stage well point system

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. For dewatering more than 6m below the water table, which of the following method is used?

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. A advantage of using jetting of water in well point system is ___________

Q. In well point system, ___________should be made essential for proper working of the system.

Q. The pump which is used for suction of water in the well point system is ___________

Q. The seepage analysis is done on the assumption of ____________

Q. For unconfined flow, which of the following discharge slot is used?

Q. Fine grained cohesive soil can be drained or stabilized by __________

Q. Discharge for a unconfined aquifer can be found from the expression developed by __________

Q. A complete design of dewatering system consist of ___________

Q. When dewatering system consist of number of well-points ___________ can be considered for a simplified solution.

Q. In discharge equation given by chapmen qp=kba(H-ho)/L+EA, EA refers to __________

Q. The application of electro-osmosis on dewatering of soil was developed by ___________

Q. For fine-grained soil what type of dewatering system can be used?

Q. The drawdown curve in fully penetrated slot is based on the assumptions of _____________

Q. A protective filter can also be called as __________

Q. The soil to be protected by protective filter is known as __________

Q. The requirements to be satisfied by a filter material were devised by which of the following organization?

Q. A protective filter is designed to provide _____________

Q. What type of filter is provided at the bottom of drainage sumps and trenches?

Q. The phreatic line of an earth dam can be kept within the body of the dam by ___________

Q. According to Terzaghi, the D15 size material must be more than the size of __________

Recommended Subjects

Are you eager to expand your knowledge beyond Geotechnical Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!