Question

The area of the pile group along the failure surface is equal to __________

a.

Perimeter × Area of cross section

b.

Breadth × Length

c.

Perimeter × Length

d.

Perimeter/area of cross section

Answer: (c).Perimeter × Length

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. The area of the pile group along the failure surface is equal to __________

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The pile spacing of each pile is taken as __________ diameter of the pile.

Q. The settlement of a group of friction piles can be computed on the assumption that ________

Q. The equation used for determining the bearing capacity of a group of friction piles is __________

Q. When the under-reamed pile has only one bulb, it is called _________

Q. The diameter of the under-reamed pile is kept equal to _______ times the diameter of pile steam.

Q. Under-reamed pile foundation is most suitable for ___________ type of condition.

Q. The load carrying capacity of a under-reamed pile may be determined by _________

Q. The under-reamed piles are connected by a beam known as ___________

Q. The maximum spacing of the under-reamed pile should not normally exceed __________

Q. Under reamed piles are normally bored _________ piles.

Q. The spacing of the piles in under-reamed pile foundation depends on which of the following factor?

Q. The grade beams are designed for a maximum bending moment of _________ if the beams are supported.

Q. The details of the depth of beam and reinforcement required for various loading is provided by_______

Q. The equipment required for construction of a under-reamed pile is________

Q. The use of bore guide in under-reamed pile foundation is essential for __________

Q. Which of the following stages are involved in the construction of under reamed piles?

Q. The depth of the bore hole is checked at _________ before insertion of the under-reamer.

Q. Routine tests are usually carried out on _________

Q. In the process of pile foundation, boring is done with the help of _________

Q. Enlarging the stem of bore hole at the depth is done by using________

Recommended Subjects

Are you eager to expand your knowledge beyond Foundation Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!