16. | X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last? |
a. | 6 days |
b. | 10 days |
c. | 15 days |
d. | 20 days |
View Answer Report Discuss 50-50! |
Answer: (b).10 days
|
17. | A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days? |
a. | 11 days |
b. | 13 days |
c. | 20(3/17) days |
d. | None of these |
View Answer Report Discuss 50-50! |
Answer: (b).13 days
|
18. | Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages? |
a. | 7 hours 30 minutes |
b. | 8 hours |
c. | 8 hours 15 minutes |
d. | 8 hours 25 minutes |
View Answer Report Discuss 50-50! |
Answer: (c).8 hours 15 minutes
|
19. | A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in: |
a. | 1/24 day |
b. | 7/24 day |
c. | 3(3/7) days |
d. | 4 days |
View Answer Report Discuss 50-50! |
Answer: (c).3(3/7) days
|
20. | Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is: |
a. | 15 |
b. | 16 |
c. | 18 |
d. | 25 |
View Answer Report Discuss 50-50! |
Answer: (b).16
|