Quality Control of Concrete Technology MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Quality Control of Concrete Technology, a fundamental topic in the field of Concrete Technology. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Quality Control of Concrete Technology MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Quality Control of Concrete Technology mcq questions that explore various aspects of Quality Control of Concrete Technology problems. Each MCQ is crafted to challenge your understanding of Quality Control of Concrete Technology principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Concrete Technology tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Quality Control of Concrete Technology MCQs are your pathway to success in mastering this essential Concrete Technology topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Quality Control of Concrete Technology. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Quality Control of Concrete Technology knowledge to the test? Let's get started with our carefully curated MCQs!

Quality Control of Concrete Technology MCQs | Page 2 of 3

Discover more Topics under Concrete Technology

Q11.
Content of SiOβ‚‚ in silica fume?
Discuss
Answer: (d).85-97%
Q12.
The property of a material that resists penetration or indentation by means of abrasion or scratching is known as ____________
Discuss
Answer: (b).Hardness
Q13.
During compression test of cast iron, the failure occurs i.e. the crack appears along the __________
Discuss
Answer: (a).Diagonal
Q14.
It opens the area of improvement for quality construction rationally based on the documents from ___________ projects.
Discuss
Answer: (a).Previous
Q15.
For walls, columns and vertical faces of all structural members, the form work is generally removed after __________
Discuss
Answer: (a).24 to 48 hours
Q16.
The basic requirement for the success of any quality control plan is the availability of experienced, knowledgeable and trained personnel at all levels.
Discuss
Answer: (a).True
Q17.
Quality control helps to ____________ the risks of overdesign that ___________ the overall cost.
Discuss
Answer: (d).Minimize, Decrease
Q18.
___________ cost of maintenance of the structure __________ construction due to quality works.
Discuss
Answer: (b).Minimize, after
Q19.
It __________ job-site concrete handling, and testing procedures to __________ potential liability to the company.
Discuss
Answer: (b).Improve, Decrease
Q20.
___________ quality construction ___________ the wastage of materials.
Discuss
Answer: (a).Good, reduce
Page 2 of 3