Well Foundations and Machine Foundations MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Well Foundations and Machine Foundations, a fundamental topic in the field of Foundation Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Well Foundations and Machine Foundations MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Well Foundations and Machine Foundations mcq questions that explore various aspects of Well Foundations and Machine Foundations problems. Each MCQ is crafted to challenge your understanding of Well Foundations and Machine Foundations principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Foundation Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Well Foundations and Machine Foundations MCQs are your pathway to success in mastering this essential Foundation Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Well Foundations and Machine Foundations. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Well Foundations and Machine Foundations knowledge to the test? Let's get started with our carefully curated MCQs!

Well Foundations and Machine Foundations MCQs | Page 4 of 8

Q31.
Laying of the well curb in river bed having water, is done by _________
Discuss
Answer: (c).Constructing cofferdams
Q32.
To avoid the setting of the cutting edge unevenly, ___________ can be introduced.
Discuss
Answer: (a).Wooden sleepers
Q33.
The inside shuttering of the well curb is made up of _________
Discuss
Answer: (c).Brick masonry
Q34.
Excavation of soil inside the well in river beds can be done by ________
Discuss
Answer: (a).Auger
Q35.
When the well is sunk deeper, the skin friction is decreased by which of the following method?
Discuss
Answer: (c).By applying kentledge
Q36.
Unequal dredging of well causes _________
Discuss
Answer: (b).Tilting
Q37.
The radius of the well curb should be kept _________ larger than the outside radius of well steining.
Discuss
Answer: (a).2 cm and 4 cm
Q38.
To counter act the tilts in the well during sinking operations, which of the following measures can be used?
Discuss
Answer: (d).All of the mentioned
Q39.
In which of the following methods, hydraulic jack is used to counter attack the tilt in the well?
Discuss
Answer: (c).Pushing by jack
Q40.
The method that is used to avoid the further increase in tilt is ___________
Discuss
Answer: (c).Strutting the well
Page 4 of 8