Hill Roads MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Hill Roads, a fundamental topic in the field of Highway Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Hill Roads MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Hill Roads mcq questions that explore various aspects of Hill Roads problems. Each MCQ is crafted to challenge your understanding of Hill Roads principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Highway Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Hill Roads MCQs are your pathway to success in mastering this essential Highway Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Hill Roads. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Hill Roads knowledge to the test? Let's get started with our carefully curated MCQs!

Hill Roads MCQs | Page 7 of 8

Q61.
The hard rock is permitted to over hang the road forming a __________
Discuss
Answer: (a).Half tunnel
Q62.
Where there is insufficient time for blasting the alternative method is?
Discuss
Answer: (d).Both cliff gallery and cradle
Q63.
What is the most important structure in a hill road?
Discuss
Answer: (a).Retaining wall
Q64.
The best type of material for retaining wall is __________
Discuss
Answer: (c).Stone masonry
Q65.
The general minimum width adopted for the retaining wall is __________
Discuss
Answer: (b).0.45 m
Q66.
The typical retaining wall is less than __________
Discuss
Answer: (a).6 m
Q67.
The width of the retaining wall foundation is taken as __________
Discuss
Answer: (a).0.4h+0.3 m
Q68.
The foundation bed is provided with a downward slope of __________ towards the hill side.
Discuss
Answer: (a).1 in 6
Q69.
The thickness of the pitching done by stone masonry to avoid erosion due to water is?
Discuss
Answer: (b).0.3 m
Q70.
Catch water drains, sloping drain, road side drains, catch pit and culverts are periodically cleared to prevent __________
Discuss
Answer: (b).Over flow of water
Page 7 of 8