Question

When is the Final Location survey done?

a.

After the particular Railway line to be constructed is decided

b.

After the Traffic survey

c.

After Reconnaissance survey

d.

Immediately after the collection of Field data

Posted under Railway Engineering

Answer: (a).After the particular Railway line to be constructed is decided

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. When is the Final Location survey done?

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. What is the objective of Final location survey?

Q. In Preliminary survey the total alignment is traversed with a Theodolite, but it is not necessary in Final location survey.

Q. In Final location survey at which points Masonry pillars are built?

Q. Which points should be considered while selecting the best alignment in Final location survey?

Q. In Characteristics of the Project Areas the geographical features of the country are given. These features do not affect the _______

Q. What does Category of a line indicates?

Q. The Permanent way section of the report does not give details about which of the following aspects?

Q. Which segment in the project report provides information and data related to the different routes that were examined for construction of the new rail line?

Q. What are the other details provided in the segment ‘Standard of construction’?

Q. Which section focuses on the problems that might be encountered, identifying areas requiring special attention and providing knowledge and information for finding solutions?

Q. Which section comments on the availability of water for various construction activities and its appropriateness for consumption?

Q. What is the order of arrangement of documents in the Report?

Q. Which among the following is not included in the Appendices to the report?

Q. Which organization provides the maps for satellite imagery?

Q. Using satellite imagery multiple corridors can be marked. After this the corridor that satisfies all the surveying criteria can be chosen.

Q. For which areas satellite imagery is most useful in the initial stages of planning?

Q. The miniature details for the preliminary survey can be can be worked out with the help of contour maps, computer aids and ______

Q. What is the first step involved in Construction of a New line?

Q. Where should one refer to for the procedure of acquisition of land with the help of member state government?

Q. If we want to construct a single line railway track, the land available should be adequate for the construction of a double line.

Recommended Subjects

Are you eager to expand your knowledge beyond Railway Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!