Embankment are laid __________

a.

Above ground level

b.

Below ground level

c.

3.0 m above ground level

d.

5.0 m above foundation level

Answer: (b).Below ground level

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Embankment are laid __________

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. What is the last step in design of embankment?

Q. If the height of embankment increases __________

Q. The fill material used in embankment is __________

Q. The settlement is due to __________

Q. The stability of foundation is checked to ensure __________

Q. Stability of slopes change with __________

Q. An embankment is classified as high if height exceeds __________

Q. What is the most common natural problem found in embankment?

Q. The investigation of embankment should be carried out for __________

Q. The consolidation can be achieved faster by __________

Q. What is the minimum spacing between the two sand beds?

Q. The liquid limit of soil for embankment construction is __________

Q. The free swelling index of soil should be less than __________

Q. The plasticity index for a sub grade should be less than __________

Q. The rollers that uses both tamping and kneading is __________

Q. The removal of earth for highway formation is __________

Q. The best time to remove soil is during __________

Q. What is the equipment used for short haul distance of 100 m?

Q. The blade angle of bulldozer is usually __________

Q. The precise control of excavation is possible by __________

Recommended Subjects

Are you eager to expand your knowledge beyond Highway Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!