Question
a.
An activity consume time and resources whereas an event do not consume time or resources.
b.
The performance of a specific task is called an activity.
c.
An event is an instantaneous point in time at which an activity begins or ends.
d.
The turning of a job on lathe is an event whereas job turned is an activity.
Posted under Mechanical Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. Which of the following statement is wrong?
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
View solution
Q. Standard time is equal to
View solution
Q. In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost.
View solution
Q. The essential condition for the decompression of an activity is that
View solution
Q. Time study is carried out
View solution
Q. Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is
View solution
Q. Which of the following are the principles of material handling?
View solution
Q. The product layout
View solution
Q. An event is a function of two or more activities.
View solution
Q. The mathematical technique for finding the best use of limited resources of a company in the maximum manner is known as
View solution
Q. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
View solution
Q. Scheduling
View solution
Q. F. W. Taylor introduced a system of organisation known as
View solution
Q. The correct sequence of phases in value engineering is
View solution
Q. Micromotion study is
View solution
Q. A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the
View solution
Q. Time study is used to
View solution
Q. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time.
View solution
Q. The main objective of work measurement is to
View solution
Q. Generally PERT is preferred over CPM for the purpose of project evaluation.
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Mechanical Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!