Question
a.
0.50
b.
0.66
c.
0.84
d.
0.95
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed...
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. Scheduling
View solution
Q. F. W. Taylor introduced a system of organisation known as
View solution
Q. The correct sequence of phases in value engineering is
View solution
Q. Micromotion study is
View solution
Q. A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the
View solution
Q. Time study is used to
View solution
Q. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time.
View solution
Q. The main objective of work measurement is to
View solution
Q. Generally PERT is preferred over CPM for the purpose of project evaluation.
View solution
Q. The bonus increases in proportion to the increase in efficiency. This statement applies to
View solution
Q. Which of the following statement is correct about the network diagram?
View solution
Q. P.M.T.S. (Predetermined Motion Time Systems) include
View solution
Q. In jobbing production
View solution
Q. Performance rating is equal to
View solution
Q. The production cost per unit can be reduced by
View solution
Q. In manufacturing management, the term 'Dispatching' is used to describe
View solution
Q. Product layout is also known as
View solution
Q. When slack of an activity is zero, the activity is critical and any delay in its performance will delay the completion of the whole project.
View solution
Q. The work study is done by means of
View solution
Q. The time taken by a trained worker to perform an operation, while working a steady pace, is known as
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Mechanical Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!