Question

Pick up the method of surveying in which field observations and plotting proceed simultaneously from the following

a.

chain surveying

b.

compass surveying

c.

plan table surveying

d.

tacheometric surveying.

Answer: (c).plan table surveying

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Pick up the method of surveying in which field observations and plotting proceed simultaneously from the following

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. While viewing through a level telescope and moving the eye slightly, a relative movement occurs between the image of the levelling staff and the cross hairs. The instrument is

Q. In chain surveying field work is limited to

Q. Two concave lenses of 60 cm focal length are cemented on either side of a convex lens of 15 cm focal length. The focal length of the combination is

Q. One of the tacheometric constants is additive, the other constant, is

Q. The limiting length of an offset does not depend upon

Q. The most reliable method of plotting a theodolite traverse, is

Q. The difference of level between a point below the plane of sight and one above, is the sum of two staff readings and an error would be produced equal to

Q. Offsets are measured with an accuracy of 1 in 40. If the point on the paper from both sources of error (due to angular and measurement errors) is not to exceed 0.05 cm on a scale of 1 cm = 20 m, the maximum length of offset should be limited to

Q. The bearings of the lines AB and BC are 146° 30' and 68° 30'. The included angle ABC is

Q. For a closed traverse the omitted measurements may be calculated

Q. The slope correction for a length of 30 m along a gradient of 1 in 20, is

Q. The main principle of surveying is to work

Q. For the construction of highway (or railway)

Q. If the radius of a simple curve is R, the length of the chord for calculating offsets by the method of chords produced, should not exceed.

Q. The sensitiveness of a level tube decreases if

Q. For true difference in elevations between two points A and B, the level must be set up

Q. ABCD is a regular parallelogram plot of land whose angle BAD is 60°. If the bearing of the line AB is 30°, the bearing of CD, is

Q. Keeping the instrument height as 1.5 m, length of staff 4 m, the slope of the ground as 1 in 10, the sight on the down-slope, must be less than

Q. Pick up the correct statement from the following :

Q. The radius of curvature of the arc of the bubble tube is generally kept

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!