Question

In the method of tube boring of soil investigation, the following is essential :

a.

a tube of about 2 metres length and 20 cm diameter with a cutting edge

b.

a flap valve at the bottom of tube is provided to extract the soil sample

c.

the tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand

d.

all the above.

Posted under Civil Engineering

Answer: (d).all the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. In the method of tube boring of soil investigation, the following is essential :

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. For each storey of a building, the depth of exploration should be

Q. Safe bearing capacity of black cotton soil varies from

Q. Crown is located at

Q. The nominal thickness of an expansion joint in brick walls, is kept more than

Q. The nominal thickness of one brick wall in mm, is

Q. The pile which supports the load partly by friction and partly by resting on hard stratum, is called

Q. To stagger vertical joints in successive courses of a wall, a piece of brick is generally used at the end of the course, which is known as

Q. The concrete slump recommended for foundations, is

Q. The minimum thickness of walls built in cement mortar (1 : 6) for a single storey building, is

Q. The form work from the slabs excluding props, can be removed only after

Q. The pile provided with one or more bulles in its vertical shaft, is generally known as

Q. To construct a 10 cm thick partition wall, you will prefer

Q. The pile which supports the load due to friction between pile face and surrounding soil, is generally known as

Q. The voussoir placed at crown of an arch, is known as a

Q. The vertical members fixed between steps and hand rail, are known

Q. Pick up the consideration to the taken while designing a hospital from the following :

Q. The form work from the sides of beams can be removed only after

Q. In soils possessing low bearing capacity, the type of foundation generally provided, is

Q. Which one of the following activities is not correct as applicable to brick corbels

Q. Pick up the correct statements from the following :

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!