Question

Unclear relative authority of the PM and the functional managers is a major component of conflicts involving

a.

Technical decisions

b.

Resource allocation

c.

Scheduling

d.

All of the Above

Answer: (d).All of the Above

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Unclear relative authority of the PM and the functional managers is a major component of conflicts involving

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. Project Formation covers some fundamental issues, which are of

Q. In a matrix organization, schedule and flow of work is managed by

Q. Maintaining the project schedule is precisely an exercise in managing

Q. The primary interest of the functional manager is the daily operation of the

Q. We can refer conflicts into the chronological perspective of the project

Q. Contracts between a firm and its suppliers, its trade unions, and its customers are written to govern the settlement of

Q. The level which includes disposition of the project?s assets and personnel, is

Q. Commitment of resources to the project must be forthcoming from

Q. In reality, trade-off decisions are extremely

Q. The Thamhain's definition of project life-cycle is a formation of

Q. At Initial stage planning is undertaken, basic objectives are adopted, and the project may be

Q. As the project's plans become detailed, conflicts build over

Q. Process which begins when one party perceives that the other has frustrated, or is about to frustrate, some concern of his, is known as

Q. The organization establishes set of rules for itself and the individuals and groups with whom it interacts in the form of

Q. Brute force can be a time-honored method for

Q. An easy-to-use approach that is well-adapted to evaluating the risk in certain situations is known as

Q. Projects involving a "disruptive" technology that is known to the industry or that the organization has been developing over time, are

Q. A process change's matrix called the aggregate project plan was developed by Wheelwright in

Q. The commitment to project portfolio process, supporting process and results is done at

Q. The short-term, medium-term, and long-term returns needs to

Recommended Subjects

Are you eager to expand your knowledge beyond Human Resource Management? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!