Question

The ratio of the increased cost for expediting to the decreased amount of time for the activity, basically is

a.

Cost-time slope

b.

Cost-performance slope

c.

Performance-time slope

d.

Quality-cost slope

Answer: (a).Cost-time slope

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. The ratio of the increased cost for expediting to the decreased amount of time for the activity, basically is

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. Resource Leveling is the approach to even out the peaks of

Q. Approaches to even out the peaks of resource requirements so that a fixed amount of resources can be employed over time, is known as

Q. The basic approaches to addressing the constrained resources allocation problem, Is of

Q. The critical path method (CPM) is a

Q. Scheduling is particularly important to projects because of

Q. The realistic approaches that may identify feasible solutions to the problem, is known as

Q. The resource allocation problem is concerned with determining the best

Q. The process of calculating the total load from project tasks on each resource for each time period is known as

Q. The evaluation of a number of alternatives that logically branch from each other, is known as

Q. A monitoring technique, that is closely related to network diagrams, Is

Q. Priority Rules are the formal methods, such as ratios, that is used for

Q. Methods that does the best allocation of resources to tasks but are limited in the size of problems they can efficiently solve, is known as

Q. A specific project task that requires resources and time to complete, is known as

Q. The activities, and data that allow information flow in a project, frequently computerized, in

Q. The audit report of evaluation should contain at least the current status of the project and

Q. A Project can be terminated in different ways of

Q. The process of terminating a project suddenly and without warning, is

Q. A project can be terminated in one of four way i.e. by extinction, addition, integration or

Q. Most projects fail because of insufficient top management support, poor planning and

Q. Special termination managers are needed, for closing out projects. The task, consists of major

Recommended Subjects

Are you eager to expand your knowledge beyond Human Resource Management? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!