Question

How many days are generally taken to obtain field capacity after free gravity drainage?

a.

3 to 7 days

b.

4 to 8 days

c.

5 to 9 days

d.

2 to 5 days

Posted under Irrigation Engineering

Answer: (d).2 to 5 days