The crest of a siphon spillway is fixed at ________________

a.

full reservoir level

b.

dead storage level

c.

maximum water level

d.

top of the dam

Posted under Irrigation Engineering

Answer: (a).full reservoir level

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. The crest of a siphon spillway is fixed at ________________

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. A siphon spillway is sufficiently independent of the water surface elevation of the reservoir.

Q. The allowable maximum negative head on an average is equal to __________

Q. The structure which is not used in a shaft spillway is ________________

Q. Morning glory is the _____________________________

Q. For a saddle siphon, the maximum operative head is 4.53 m. The width and height of the throat of the siphon are 5 m and 2.25 m respectively. The coefficient of discharge is 0.90. How many units are required to pass a flood of 350 cumecs? (Assume g = 10 m/s2)

Q. A siphon spillway in a concrete gravity dam is in the shape of ________________

Q. The energy dissipation at the toe of the spillway is affected basically by the use of hydraulic jump in _______________________

Q. The most ideal condition for energy dissipation in the design of spillways is the one when the tail-water rating curve coincides with the jump rating curve at all discharge.

Q. When the tail-water depths in the river downstream of a spillway are quite low such that the tail-water curve at all discharges lies below the post jump depth curve, then the energy dissipation can be affected best by ___________________

Q. The device which does not help in energy dissipation at the bottom of a hydraulic structure over which water spills is ________________

Q. The formation of hydraulic jump at the foot of a spillway is one of the common methods of energy dissipation because ______________________

Q. A ski-jump bucket is also known as _____________________

Q. The percentage of energy dissipation in a hydraulic jump increases with the increase in the Froude number.

Q. Which of the following stilling basin help in stabilizing the flow and improve the jump performance?

Q. What is the expected solution for the case when the T.W.C is lying above the J.H.C curve at all discharges?

Q. A sloping apron is provided partly above the river bed and partly below the river bed in case of ____________________________

Q. When the TWC lies below the JHC at all discharges, the problem can be solved by which of the following provisions?

i. Constructing a sloping apron above the river bed
ii. Provision of roller bucket type of energy dissipator
iii. Provision of a ski-jump bucket
iv. A sloping apron below the river bed
v. Construction of a subsidiary dam
vi. A sloping apron partly above and partly below the river bed

Q. A troublesome and oscillating hydraulic jump is normally met in cases of _____________

Q. A very steady and stable hydraulic jump is usually formed in the flows involving the approaching Froude number in the range of _____________________

Q. Standard USBR stilling basin-II is useful for energy dissipation at the bottom of the overflow structure, if the approaching Froude number is ________________