Question

When the allowable soil is low or the building loads are heavy, the footing used is ___________

a.

Raft footing

b.

Strap footing

c.

Trapezoidal combined footing

d.

Rectangular combined footing

Posted under Foundation Engineering

Answer: (a).Raft footing

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. When the allowable soil is low or the building loads are heavy, the footing used is ___________

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. If the resultant of the soil pressure coincides with the resultant of the loads, the soil is pressure is assumed to be ____________

Q. In designing rectangular combined footing _________ should be adopted as the design value.

Q. For a rectangular combined footing, x̅ is given as ___________

Q. Generally combined footing is assumed to rest on ___________

Q. The design procedure of strap footing is essentially that of _____________

Q. What will be the shape of footing if a=0, is substituted in the pressure intensity equation “q2 = a. qs”?

Q. The foundation that is used when the soil mass is sufficiently erratic?

Q. Usually, rafts are designed as _________

Q. The weight of the raft is not considered in the structural design, because ___________

Q. If a maximum settlement of 50 mm is permitted for a raft, the differential settlement must not exceed ___________

Q. The net ultimate bearing capacity for raft may be determined by __________

Q. In raft footing, if the C.G of the load coincide with the centroid of the raft, the upward load is considered as ___________

Q. Raft is subdivided in to series of beams to establish __________

Q. The penetration resistance N for designing of raft should be taken at ___________ intervals.

Q. If the penetration resistance N is less than 5, which of the following measures can be adopted?

Q. The net pressure can be calculated for raft having width greater than ___________

Q. According to IS codes, the maximum differential settlements should not exceed ___________ in the foundation on clayey soil.

Q. The possible method adopted for designing of raft foundation is ___________

Q. The conventional method for designing raft foundation is based on which of the following assumptions?

Q. The actual reinforcement provided should be ___________ of that worked out theoretically by conventional method.

Recommended Subjects

Are you eager to expand your knowledge beyond Foundation Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!