Question
a.
Dynamic formulae
b.
Static formulae
c.
Feld’s formulae
d.
Hiley’s formulae
Posted under Foundation Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. Which of the following formulae can be used for determining the efficiency of pile group?
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. In which of the following rule, the value of each pile is reduced by one-sixteenth?
View solution
Q. The bearing capacity of a single pile in clay is mainly due to _________
View solution
Q. The downward drag acting on a pile due to the movement of the surrounding is called ________
View solution
Q. The area of the pile group along the failure surface is equal to __________
View solution
Q. The pile spacing of each pile is taken as __________ diameter of the pile.
View solution
Q. The settlement of a group of friction piles can be computed on the assumption that ________
View solution
Q. The equation used for determining the bearing capacity of a group of friction piles is __________
View solution
Q. When the under-reamed pile has only one bulb, it is called _________
View solution
Q. The diameter of the under-reamed pile is kept equal to _______ times the diameter of pile steam.
View solution
Q. Under-reamed pile foundation is most suitable for ___________ type of condition.
View solution
Q. The load carrying capacity of a under-reamed pile may be determined by _________
View solution
Q. The under-reamed piles are connected by a beam known as ___________
View solution
Q. The maximum spacing of the under-reamed pile should not normally exceed __________
View solution
Q. Under reamed piles are normally bored _________ piles.
View solution
Q. The spacing of the piles in under-reamed pile foundation depends on which of the following factor?
View solution
Q. The grade beams are designed for a maximum bending moment of _________ if the beams are supported.
View solution
Q. The details of the depth of beam and reinforcement required for various loading is provided by_______
View solution
Q. The equipment required for construction of a under-reamed pile is________
View solution
Q. The use of bore guide in under-reamed pile foundation is essential for __________
View solution
Q. Which of the following stages are involved in the construction of under reamed piles?
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Foundation Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!