Chain Rule MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Chain Rule, a fundamental topic in the field of Aptitude. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Chain Rule MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Chain Rule mcq questions that explore various aspects of Chain Rule problems. Each MCQ is crafted to challenge your understanding of Chain Rule principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Aptitude tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Chain Rule MCQs are your pathway to success in mastering this essential Aptitude topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Chain Rule. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Chain Rule knowledge to the test? Let's get started with our carefully curated MCQs!

Chain Rule MCQs | Page 2 of 2

Discover more Topics under Aptitude

Q11.
A flagstaff 17.5 m high casts a shadow of length 40.25 m. The height of the building, which casts a shadow of length 28.75 m under similar conditions will be:
Discuss
Answer: (b).12.5 m
Q12.
In a camp, there is a meal for 120 men or 200 children. If 150 children have taken the meal, how many men will be catered to with remaining meal?
Discuss
Answer: (b).30
Q13.
An industrial loom weaves 0.128 metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metres of cloth?
Discuss
Answer: (b).195
Q14.
36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?
Discuss
Answer: (d).24
Q15.
4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat-weavers in 8 days?
Discuss
Answer: (d).16