Lining of Irrigation Canals MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Lining of Irrigation Canals, a fundamental topic in the field of Irrigation Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Lining of Irrigation Canals MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Lining of Irrigation Canals mcq questions that explore various aspects of Lining of Irrigation Canals problems. Each MCQ is crafted to challenge your understanding of Lining of Irrigation Canals principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Irrigation Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Lining of Irrigation Canals MCQs are your pathway to success in mastering this essential Irrigation Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Lining of Irrigation Canals. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Lining of Irrigation Canals knowledge to the test? Let's get started with our carefully curated MCQs!

Lining of Irrigation Canals MCQs | Page 2 of 6

Q11.
A lined canal costs about 2 to 2.5 times as much as the unlined canal.
Discuss
Answer: (a).True
Q12.
Which of the following is not an advantage of the lining of the canal?
Discuss
Answer: (d).Increased maintenance costs
Q13.
The capacity of the channel is a function of velocity.
Discuss
Answer: (a).True
Q14.
What is the range of value of Manning’s coefficient for straight alignment for cast in-situ concrete lining?
Discuss
Answer: (b).0.015 – 0.018
Q15.
Lining decreases the channel capacity and consequently reduces the required channel section.
Discuss
Answer: (b).False
Q16.
Removal of silt considerably reduces the annual expenditure required on unlined channels for desilting.
Discuss
Answer: (a).True
Discuss
Answer: (c).The lining does not reduce the money spent in removing weeds
Discuss
Answer: (d).The lining does not help to bring high areas under the command
Discuss
Answer: (b).Triangular and Trapezoidal channel
Q20.
What is the maximum permissible velocity in Cement concrete lining (Unreinforced) as per Indian Standards?
Discuss
Answer: (a).2 to 2.5 m/sec
Page 2 of 6