Industrial Engineering and Production Management MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Industrial Engineering and Production Management, a fundamental topic in the field of Mechanical Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Industrial Engineering and Production Management MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Industrial Engineering and Production Management mcq questions that explore various aspects of Industrial Engineering and Production Management problems. Each MCQ is crafted to challenge your understanding of Industrial Engineering and Production Management principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Mechanical Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Industrial Engineering and Production Management MCQs are your pathway to success in mastering this essential Mechanical Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Industrial Engineering and Production Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Industrial Engineering and Production Management knowledge to the test? Let's get started with our carefully curated MCQs!

Industrial Engineering and Production Management MCQs | Page 11 of 17

Discover more Topics under Mechanical Engineering

Q101.
Which one of the following techniques is used for determining allowances in time study?
Discuss
Answer: (d).Work sampling
Q102.
If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by
Discuss
Answer: (c).โˆš(AP/C)
Discuss
Answer: (a).single time estimate
Discuss
Answer: (b).is applied to all level of workers
Q105.
Which of the following wage incentive plan is applied to all workers?
Discuss
Answer: (a).Halsey plan
Q106.
Actual performance of a task is called
Discuss
Answer: (b).an activity
Q107.
Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?
Discuss
Answer: (a).Halsey plan
Discuss
Answer: (a).relative values of a job
Q109.
The routing function in a production system design is concerned with
Discuss
Answer: (c).machine utilisation
Q110.
The determination of standard time in a complex job system is best done through
Discuss
Answer: (d).analysis of standard data system