Industrial Engineering and Production Management MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Industrial Engineering and Production Management, a fundamental topic in the field of Mechanical Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Industrial Engineering and Production Management MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Industrial Engineering and Production Management mcq questions that explore various aspects of Industrial Engineering and Production Management problems. Each MCQ is crafted to challenge your understanding of Industrial Engineering and Production Management principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Mechanical Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Industrial Engineering and Production Management MCQs are your pathway to success in mastering this essential Mechanical Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Industrial Engineering and Production Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Industrial Engineering and Production Management knowledge to the test? Let's get started with our carefully curated MCQs!

Industrial Engineering and Production Management MCQs | Page 12 of 17

Discover more Topics under Mechanical Engineering

Discuss
Answer: (b).(Crash Cost - Normal cost)/ (Normal time - Crash time)
Q112.
If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be
Discuss
Answer: (d).TR + [(S - T)/S] × R
Discuss
Answer: (d).all of these
Discuss
Answer: (d).all of the above
Discuss
Answer: (c).minimise the cost without change in quality of the product
Q116.
In time study, the rating factor is applied to determine
Discuss
Answer: (d).normal time of a worker
Discuss
Answer: (c).production schedule
Discuss
Answer: (d).all of these
Q119.
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
Discuss
Answer: (d).(to + tp + 4tn)/6
Q120.
Bar chart is suitable for
Discuss
Answer: (c).minor work