Project Survey MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Project Survey, a fundamental topic in the field of Surveying. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Project Survey MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Project Survey mcq questions that explore various aspects of Project Survey problems. Each MCQ is crafted to challenge your understanding of Project Survey principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Surveying tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Project Survey MCQs are your pathway to success in mastering this essential Surveying topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Project Survey. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Project Survey knowledge to the test? Let's get started with our carefully curated MCQs!

Project Survey MCQs | Page 1 of 11

Discover more Topics under Surveying

Q1.
Which of the following is not a stage of railway line survey procedure?
Discuss
Answer: (a).Marine survey
Q2.
Reconnaissance survey is done in case of railway line alignment.
Discuss
Answer: (a).True
Q3.
Which of the following must be considered while laying an alignment?
Discuss
Answer: (d).Population
Q4.
Alignment considered must be _________
Discuss
Answer: (c).Short
Q5.
While designing an alignment number of curves should be more.
Discuss
Answer: (b).False
Q6.
Which of the following is used while selecting an alignment for railway line?
Discuss
Answer: (d).Soil survey
Q7.
Which of the following comes under the preliminary survey of the railway line?
Discuss
Answer: (b).Establishment of bench marks
Q8.
Which process must be adopted before selecting an alignment?
Discuss
Answer: (c).Preliminary survey
Q9.
The final survey report consist which of the following?
Discuss
Answer: (d).Revenue of the project
Q10.
Along with the final report which of the following are to be attached?
Discuss
Answer: (b).Route survey map