Sewage Filters MCQs

Welcome to our comprehensive collection of Multiple Choice Questions (MCQs) on Sewage Filters, a fundamental topic in the field of Waste Water Engineering. Whether you're preparing for competitive exams, honing your problem-solving skills, or simply looking to enhance your abilities in this field, our Sewage Filters MCQs are designed to help you grasp the core concepts and excel in solving problems.

In this section, you'll find a wide range of Sewage Filters mcq questions that explore various aspects of Sewage Filters problems. Each MCQ is crafted to challenge your understanding of Sewage Filters principles, enabling you to refine your problem-solving techniques. Whether you're a student aiming to ace Waste Water Engineering tests, a job seeker preparing for interviews, or someone simply interested in sharpening their skills, our Sewage Filters MCQs are your pathway to success in mastering this essential Waste Water Engineering topic.

Note: Each of the following question comes with multiple answer choices. Select the most appropriate option and test your understanding of Sewage Filters. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

So, are you ready to put your Sewage Filters knowledge to the test? Let's get started with our carefully curated MCQs!

Sewage Filters MCQs | Page 12 of 14

Discuss
Answer: (b).Clariflocculator
Q112.
Which of these don’t require a flash mixer and a flocculator prior to it?
Discuss
Answer: (a).High rate solid contact clarifier
Discuss
Answer: (a).High rate solid contact clarifier
Q114.
While designing a clarifier what is the maximum limit velocity that is assumed?
Discuss
Answer: (a).1.5 m/h
Q115.
While designing a clariflocculator what is the maximum limit velocity that is assumed?
Discuss
Answer: (b).2.0 m/h
Q116.
While designing an HRSCC what is the velocity assumed?
Discuss
Answer: (c).3 m/h
Q117.
While designing a clariflocculator what is the maximum detention time assumed for the flocculation zone?
Discuss
Answer: (a).40 mins
Q118.
While designing an HRSCC what is the detention time assumed for the draft tube?
Discuss
Answer: (a).60 secs
Q119.
While designing an HRSCC what is the detention time assumed for the detention hood?
Discuss
Answer: (c).120 secs
Q120.
While designing an HRSCC what is the Solid loading rate assumed for the Clarification zone?
Discuss
Answer: (d).0.9 m/h