Question

Which of the following is associated with developing the processes that are needed to deliver quality products or services complying with customer needs?

a.

Quality Planning

b.

Quality Control

c.

Quality Improvement

d.

Quality Assurance

Answer: (a).Quality Planning

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Which of the following is associated with developing the processes that are needed to deliver quality products or services complying with customer needs?

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The planning of periodic checks and inspection to ensure product specifications and features are met is associated with __________

Q. The process of checking the actual performance with the standard performance is associated with __________

Q. The process of identifying the scope for process improvement is associated with ________

Q. Juran’s Trilogy diagram is a plot between ______ and _______

Q. According to Juran’s Trilogy diagram, errors made in the planning process give rise to _________

Q. According to Juran’s Trilogy diagram, errors made in the quality control process give rise to ________

Q. Sporadic waste can be identified and corrected through quality control.

Q. Chronic waste requires improvement process.

Q. Juran’s Trilogy is a ______ and ______ continuous process improvement approach.

Q. Who gave the classification of five types of quality problems?

Q. When a structured system having standardized inputs, processes, and outputs is performing unacceptably from the customer’s point of view, then we have _________

Q. Compliance problems can be identified by comparing with standards or by collecting feedback from internal and/or external customers.

Q. How are unstructured problems different from compliance problems?

Q. Unstructured problems can be identified through negative customer feedback.

Q. When the system is performing unacceptably from the owner’s point of view, then we have _________

Q. Efficiency problems can be identified by ____________ and ___________

Q. Which of the following cannot be considered as a motivation behind identification of process-design problems?

Q. Process-design problems involve the revision of ___________ and the development of ___________

Q. Product-design problems involve the improvement of ___________ and the development of ___________

Q. Product-design problems arise due to changing ____________ or competitor coming up with a better product.

Recommended Subjects

Are you eager to expand your knowledge beyond Total Quality Management? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!