Question

Dummy activities are used to

a.

determine the critical path

b.

determine the project completion time

c.

maintain the required net work

d.

none of these

Posted under Mechanical Engineering

Answer: (c).maintain the required net work

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Dummy activities are used to

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. Which of the following statement is wrong?

Q. The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of

Q. Standard time is equal to

Q. In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost.

Q. The essential condition for the decompression of an activity is that

Q. Time study is carried out

Q. Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

Q. Which of the following are the principles of material handling?

Q. The product layout

Q. An event is a function of two or more activities.

Q. The mathematical technique for finding the best use of limited resources of a company in the maximum manner is known as

Q. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

Q. Scheduling

Q. F. W. Taylor introduced a system of organisation known as

Q. The correct sequence of phases in value engineering is

Q. Micromotion study is

Q. A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the

Q. Time study is used to

Q. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time.

Q. The main objective of work measurement is to

Recommended Subjects

Are you eager to expand your knowledge beyond Mechanical Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!