Question

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

a.

A

b.

B

c.

C

d.

D

Posted under Civil Engineering

Answer: (c).C

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:

Q. For the network shown in the given figure, the expected time for the activity

Q. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the

Q. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

Q. The performance of a specific task in CPM, is known

Q. Pick up the correct statement from the following:

Q. A Milestone chart

Q. Completion of an activity on CPM network diagram, is generally known

Q. A dummy activity

Q. The difference between the time avail-to do a job and the time required to do the job, is known as

Q. The object of technical planning, is

Q. The salient feature of functional organisation is

Q. Critical path method

Q. CPM is

Q. Which one of the following represents an activity

Q. Pick up the incorrect statement from the following:

Q. The technique for establishing and maintaining priorities among the various jobs of a project, is known

Q. Mile Stone charts were invented in the year of

Q. Frederick W. Taylor introduced a system of working known as

Q. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!