Question
a.
Event flow scheduling technique
b.
Critical ratio scheduling
c.
Slotting technique for scheduling
d.
Short interval scheduling.
Posted under Civil Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. The technique for establishing and maintaining priorities among the various jobs of a project, is known
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. Mile Stone charts were invented in the year of
View solution
Q. Frederick W. Taylor introduced a system of working known as
View solution
Q. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
View solution
Q. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
View solution
Q. Modular co-ordination of construction means proper
View solution
Q. Pick up the correct statement from the following:
View solution
Q. Critical path lies along the activities having total float
View solution
Q. Construction team means
View solution
Q. A construction schedule is prepared after collecting
View solution
Q. Site order book is used for recording
View solution
Q. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
View solution
Q. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
View solution
Q. Henry Gantt developed Bar charts for planning and scheduling of projects in
View solution
Q. The most popular type of organisation used for Civil Engineering Constructions, is
View solution
Q. Pick up the PERT event from the following:
View solution
Q. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
View solution
Q. Final technical authority of a project lies with
View solution
Q. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
View solution
Q. Works costing less than Rs. 20,000 are treated as
View solution
Q. A critical ratio scheduling
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!