Question

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

a.

started 5 days later

b.

completed 5 days later

c.

performed at slower rate in 15 days

d.

all the above.

Posted under Civil Engineering

Answer: (d).all the above.