Question
a.
to concentrate his attention on critical activities
b.
to divert the resources from non-critical advanced activities to critical activities
c.
to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
d.
all the above.
Posted under Construction Management Civil Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. Critical Path Net Work helps an engineer
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. Pick up the correct statement from the following:
View solution
Q. Which one of the following represents an event ?
View solution
Q. Pick up the incorrect statement from the following:
View solution
Q. Frequency distribution curves
View solution
Q. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
View solution
Q. Pick up the correct statement from the following:
View solution
Q. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
View solution
Q. For the execution of a project, a contractor is
View solution
Q. Railway projects are treated as
View solution
Q. Pick up the correct statement from the following:
View solution
Q. The critical activity has
View solution
Q. The main disadvantage of line organisation, is
View solution
Q. Pick up the correct statement from the following:
View solution
Q. Pre-tender stage requires
View solution
Q. Power stations are generally treated as
View solution
Q. An event is indicated on the network by a number enclosed in
View solution
Q. Pick up the incorrect statement from the following:
View solution
Q. While scheduling a project by C.P.M.
View solution
Q. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
View solution
Q. The final selection of a construction site, is done by
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!