Question

Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

a.

Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

b.

Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity

c.

The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time

d.

All the above.

Posted under Civil Engineering

Answer: (d).All the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!