Question

PERT is

a.

an analytic in concept

b.

limited of event oriented diagrams

c.

used for research and development projects

d.

all the above.

Answer: (d).all the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. PERT is

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The first stage of a construction, is

Q. Pick up the correct statement from the following:

Q. The final selection of a construction site, is done by

Q. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

Q. While scheduling a project by C.P.M.

Q. Pick up the incorrect statement from the following:

Q. An event is indicated on the network by a number enclosed in

Q. Power stations are generally treated as

Q. Pre-tender stage requires

Q. Pick up the correct statement from the following:

Q. The main disadvantage of line organisation, is

Q. The critical activity has

Q. Pick up the correct statement from the following:

Q. Railway projects are treated as

Q. For the execution of a project, a contractor is

Q. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

Q. Pick up the correct statement from the following:

Q. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

Q. Frequency distribution curves

Q. Pick up the incorrect statement from the following:

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!