Question

If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

a.

(t1 - t2) - t

b.

t - (t1 - t2)

c.

(t1 + t2) - t

d.

t + (t1 - t2)

Posted under Civil Engineering

Answer: (a).(t1 - t2) - t