Question
a.
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
b.
The difference between the maximum time available for the job and actual time it consumes, is called total float
c.
The difference between the latest start time and earliest start time of an activity, is called total float
d.
None of these.
Posted under Civil Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. Pick up the incorrect statement from the following:
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. While scheduling a project by C.P.M.
View solution
Q. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
View solution
Q. The final selection of a construction site, is done by
View solution
Q. Pick up the correct statement from the following:
View solution
Q. The first stage of a construction, is
View solution
Q. PERT is
View solution
Q. Residential buildings are treated as
View solution
Q. The main advantage of line organisation, is :
View solution
Q. PERT analysis is based on
View solution
Q. For completion of a project, the critical path of the network represents
View solution
Q. In CPM analysis,
View solution
Q. A goiden rule for the procurement of construction stones, suggests
View solution
Q. Pick up the correct statement from the following:
View solution
Q. While filling the tender for any work, the contractor considers
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!