Question

Pick up the PERT event from the following:

a.

Digging of foundation started

b.

Digging of foundation completed

c.

Laying of concrete started

d.

All the above.

Posted under Civil Engineering

Answer: (d).All the above.

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Pick up the PERT event from the following:

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

Q. Final technical authority of a project lies with

Q. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Q. Works costing less than Rs. 20,000 are treated as

Q. A critical ratio scheduling

Q. Bar charts are suitable for

Q. The first method invented for planning projects, was

Q. An Executive Engineer may have powers upto

Q. The main principle of an organisation, is

Q. The estimated time required to perform an activity, is known as

Q. A CPM family includes

Q. The time which results in the leasi, possible construction cost of an activity, is known

Q. Military organisation is known as

Q. Pick up the incorrect statement from the following:

Q. Various activities of a project, are shown on bar charts by

Q. Time and progress chart of a construction, is also known as

Q. Critical Path Net Work helps an engineer

Q. Pick up the correct statement from the following:

Q. Which one of the following represents an event ?

Q. Pick up the incorrect statement from the following:

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!