Question

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

a.

EF = ES + D

b.

LS = LF - D

c.

LF = LS + D

d.

all the above.

Posted under Civil Engineering

Answer: (d).all the above.