Question

Pick up the excavation where measurements are made in square metres for payment.

a.

Ordinary cuttings up to 1 m

b.

surface dressing up to 15 cm depths

c.

Surface excavation up to 30 cm depths

d.

Both (b) and (c)

Answer: (d).Both (b) and (c)

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Pick up the excavation where measurements are made in square metres for payment.

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. The expected out turn of 2.5 cm cement concrete floor per manson per day

Q. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

Q. The order of booking dimensions is

Q. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken

Q. Pick up the item of work not included in the plinth area estimate

Q. Pick up the correct statement from the following:

Q. The brick work is measured in sq metre, in case of

Q. Brick walls are measured in sq. m if the thickness of the wall is

Q. The most reliable estiamte is

Q. The expected out turn of 12 mm plastering with cement mortar is

Q. The main factor to be considered while preparing a detailed estimate, is

Q. The damp proof course (D.P.C.) is measured in

Q. Pick up the incorrect statement regarding a master trap from the following :

Q. The concrete work for the following part of the building of specified thickness is measured in square metres

Q. Pick up the correct statement from the following:

Q. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

Q. The measurement is not made in square metres in case of

Q. According to ISI method of measurement, the order of the sequence is

Q. The assumption on which the trapezoidal formula for volumes is based, is

Q. The cross-sections for a highway is taken at

Recommended Subjects

Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!