Question
a.
26, 000 m³
b.
26, 500 m³
c.
27, 000 m³
d.
27, 500 m³
Posted under Civil Engineering
Interact with the Community - Share Your Thoughts
Uncertain About the Answer? Seek Clarification Here.
Understand the Explanation? Include it Here.
Q. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m...
Similar Questions
Explore Relevant Multiple Choice Questions (MCQs)
Q. The order of booking dimensions is
View solution
Q. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken
View solution
Q. Pick up the item of work not included in the plinth area estimate
View solution
Q. Pick up the correct statement from the following:
View solution
Q. The brick work is measured in sq metre, in case of
View solution
Q. Brick walls are measured in sq. m if the thickness of the wall is
View solution
Q. The most reliable estiamte is
View solution
Q. The expected out turn of 12 mm plastering with cement mortar is
View solution
Q. The main factor to be considered while preparing a detailed estimate, is
View solution
Q. The damp proof course (D.P.C.) is measured in
View solution
Q. Pick up the incorrect statement regarding a master trap from the following :
View solution
Q. The concrete work for the following part of the building of specified thickness is measured in square metres
View solution
Q. Pick up the correct statement from the following:
View solution
Q. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
View solution
Q. The measurement is not made in square metres in case of
View solution
Q. According to ISI method of measurement, the order of the sequence is
View solution
Q. The assumption on which the trapezoidal formula for volumes is based, is
View solution
Q. The cross-sections for a highway is taken at
View solution
Q. The detention period in a septic tank is assumed
View solution
Q. The area is measured correct to the nearest
View solution
Recommended Subjects
Are you eager to expand your knowledge beyond Civil Engineering? We've handpicked a range of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!