Question

Hard foundations are generally available in non-alluvial soils.

a.

True

b.

False

c.

May be True or False

d.

Can't say

Posted under Irrigation Engineering

Answer: (a).True

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. Hard foundations are generally available in non-alluvial soils.

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. A canal which when fully developed yields enough revenue to cover up its running cost is known as _____________

Q. Which type of canal does not need cross drainage structures?

Q. What is the name given to the junction of two streams?

Q. On flatlands what type of canal alignment is used?

Q. A canal aligned on the watershed saves the cost of constructed cross drainage works.

Q. Which type of canal is most useful in hilly areas?

Q. Contour canal can irrigate only on one side of the canal.

Q. What type of canal necessitates construction of cross drainage works more than any other types?

Q. Which type of canal is the farmer’s responsibility?

Q. Which type of canal need syphons?

Q. If a looping is present in the ridge line they how can that area be irrigated with?

Q. A curve in channel results in _____________

Q. If the discharging capacity of the channel is less than 0.5 cumecs then, the minimum recommended value for curve radius is _________

Q. The Gross Command Area (G.C.A) represents the geographical area of the Doab.

Q. What is the Annual Intensity of irrigation (AII)?

Q. What is Gross Cropped Area?

Q. The ratio of the actual operating period of a distributary to the crop period is called as ____________

Q. The number of hectares irrigable per cumec of the canal capacity at its head is known as ____________

Q. The cropped area in Rabi season is usually increased.

Q. The Gross Command Area for a distributary is 8000 hectares 80% of which is culturable irrigable. The intensity of irrigation for Rabi season is 50% and the average duty at the head of the distributary is 2000 hectares/cumec. Determine the discharge required at the head of the distributary.

Recommended Subjects

Are you eager to expand your knowledge beyond Irrigation Engineering? We've handpicked a range of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of various subjects. Happy exploring!