Question

The type of canal alignment which involves maximum CD works is a ______________

a.

ridge canal

b.

contour canal

c.

side slope canal

d.

both ridge and contour canal

Answer: (b).contour canal

Interact with the Community - Share Your Thoughts

Uncertain About the Answer? Seek Clarification Here.

Understand the Explanation? Include it Here.

Q. The type of canal alignment which involves maximum CD works is a ______________

Similar Questions

Explore Relevant Multiple Choice Questions (MCQs)

Q. What is Lacey’s equation for fixing the approximate value of the required waterway for the drain?

Q. The maximum permissible reduction in the waterway from Lacey’s perimeter is _______

Q. The permissible velocity through the barrels is generally limited to _____________

Q. Which of the following method is applicable for the design of channel transition when the water depths of the flumed and unflumed section are the same or maybe different?

Q. In a siphon aqueduct, the worst condition of uplift on the floor occurs when ________

Q. To reduce the cost of the CD works we resort to _____

Q. The greater is the fluming, the greater is the length of upstream and downstream transition wings.

Q. Which of the following wings protect the earthen slopes of the canal and also guide the drainage water?

Q. The head loss through a siphon barrel is usually given by Unwin’s formula by neglecting velocity of approach as HL = [1 + F₁ + F₂. L/R] V²/2g, where F₁ and F₂ respectively represent the coefficient of head losses due to?

Q. The floor of a siphon aqueduct needs to be designed for conditions when?

i. The canal and drainage are flowing full
ii. The canal is full and there is no drainage discharge
iii. The canal is empty and drainage discharge is full

Q. A siphon aqueduct is constructed at a canal crossing site where drainage HFL was 212.2 m by allowing an afflux of 0.4 m at high flood discharge. At this site, the water level downstream of the crossing at the same high flood will be _________

Q. Calculate the depth of cut-off for scour holes for an irrigation channel of F.S.Q equal to 354 cumecs and H.F.Q of natural drainage equal to 600 cumecs. Assume the value of friction factor as 1.

Q. Calculate the value of hydraulic mean radius for a channel designed by Lacey’s theory which has a mean velocity of 1m/sec. The silt factor can be taken as unity.

Q. Which of the following is usually adopted for contraction and construction joints?

Q. Which of the following is not a movement joint?

Q. A partial contraction joint is the one in which?

Q. Which of the following is a movement joint with deliberate discontinuity but no initial gap?

Q. Which of the following is a movement joint with complete discontinuity in both reinforcement and concrete and intended to accommodate either expansion or contraction of the structure?

Q. In reinforced concrete floors, the movement joints should normally be spaced at a maximum spacing of ____________

Q. The expansion joints in floors and walls should normally be provided at a spacing of not more than ___________

Recommended Subjects